Tough floors. Beautiful finish. 601-319-9619
Home About
Services Services
Systems Epoxy Flooring Metallic Epoxy Garage Epoxy Flake Epoxy Commercial Epoxy Industrial Epoxy Concrete Polishing Concrete Grinding Concrete Sealing Grind and Seal Quartz Systems Urethane Cement Patio Coatings Pool Deck Coatings
Automotive Auto Shop Epoxy Auto Detailing Epoxy Collision Shop Epoxy Vinyl Wrap Shop Epoxy Tire Shop Epoxy Car Wash Epoxy Dealership Showroom Epoxy Quick Lube Epoxy Diesel Shop Epoxy Motorcycle Shop Epoxy Powersports Dealership Epoxy Aircraft Hangar Epoxy Boat Repair Shop Epoxy
Retail Smoke Shop Epoxy Dispensary Epoxy Liquor Store Epoxy Gas Station Epoxy Grocery Store Epoxy Clothing Store Epoxy Showroom Epoxy Nightclub Epoxy Brewery Epoxy Coffee Shop Epoxy Hotel Lobby Epoxy Restaurant Epoxy
Fitness Gym Floor Epoxy CrossFit Gym Epoxy MMA Gym Epoxy Yoga Studio Epoxy Dance Studio Epoxy Indoor Sports Facility Epoxy Trampoline Park Epoxy Bowling Alley Epoxy Arcade Epoxy Locker Room Epoxy
Medical Medical Office Epoxy Dental Office Epoxy Veterinary Clinic Epoxy Pharmacy Epoxy Hospital Epoxy Cleanroom Epoxy Physical Therapy Clinic Epoxy
Industrial Warehouse Epoxy Food Processing Plant Epoxy Cold Storage Epoxy Chemical Plant Epoxy Aerospace Facility Epoxy Distribution Center Epoxy Loading Dock Epoxy
Trades Barbershop Epoxy Tattoo Shop Epoxy Nail Salon Epoxy Pet Grooming Epoxy Dog Kennel Epoxy Self Storage Epoxy Print Shop Epoxy Maker Space Epoxy
Institutional School Epoxy Daycare Epoxy Church Epoxy Community Center Epoxy
Areas Service Areas
Mississippi
Attala County, MS Attala County, MS Sand Hill, MS
Forrest County, MS Forrest County, MS Hattiesburg, MS
Greene County, MS Greene County, MS Leakesville, MS
Hancock County, MS Hancock County, MS Bay St. Louis, MS Diamondhead, MS Kiln, MS Waveland, MS
Harrison County, MS Harrison County, MS Biloxi, MS DeLisle, MS Gulfport, MS Long Beach, MS Pass Christian, MS
Hinds County, MS Hinds County, MS Byram, MS Clinton, MS Terry, MS
Jackson County, MS Jackson County, MS Big Point, MS Gautier, MS Gulf Hills, MS Gulf Park Estates, MS Latimer, MS Moss Point, MS Ocean Springs, MS Pascagoula, MS Vancleave, MS
Jones County, MS Jones County, MS
Ellisville, MS Ellisville, MS Garage Epoxy Patio Coatings Concrete Polishing Commercial Epoxy Metallic Epoxy
Laurel, MS
Lamar County, MS Lamar County, MS Lumberton, MS Oak Grove, MS Purvis, MS
Lauderdale County, MS Lauderdale County, MS Collinsville, MS Meridian Station, MS
Madison County, MS Madison County, MS Gluckstadt, MS Madison, MS
Neshoba County, MS Neshoba County, MS Pearl River, MS
Pearl River County, MS Pearl River County, MS Picayune, MS Poplarville, MS
Rankin County, MS Rankin County, MS Brandon, MS Cleary, MS Florence, MS Flowood, MS Goshen Springs, MS Langford, MS Monterey, MS Pearl, MS Piney Woods, MS Puckett, MS Robinhood, MS
Scott County, MS Scott County, MS Sebastopol, MS
Simpson County, MS Simpson County, MS Magee, MS Mendenhall, MS
Stone County, MS Stone County, MS McHenry, MS
Walthall County, MS Walthall County, MS Tylertown, MS
Alabama
Baldwin County, AL Baldwin County, AL Foley, AL Gulf Shores, AL Orange Beach, AL Robertsdale, AL
Clarke County, AL Clarke County, AL Jackson, AL Thomasville, AL
Mobile County, AL Mobile County, AL Mobile, AL
Louisiana
St. Tammany Parish, LA St. Tammany Parish, LA Covington, LA Madisonville, LA Mandeville, LA Slidell, LA
Finishes Gallery Blog Contact Call · 601-319-9619
Skip to content

Coating a working floor without shutting the doors

The first question a shop owner asks is never about the floor. It is how many days they lose, and the answer they are hoping for is none.

Usually that is achievable. Very few of the commercial floors we do require a business to lock up and go home, but getting there takes planning that happens before anybody turns up with a grinder. The plan is mostly about three things: where the walls between work and business are going to be, when the noisy part happens, and which hours of the clock belong to the chemistry rather than to the schedule. Get those agreed in advance and a working building stays working. Decide them on the morning of day one and somebody ends up walking across a floor that was not ready for them.

Sections, not phases

The usual shape is to split the floor into sections and take them one at a time, with a hard physical boundary around whatever we are in. Not tape on the ground. An actual barrier, because the single most expensive thing that can happen on a commercial job is a member of staff cutting through a cured-but-not-ready area to save thirty seconds.

Choosing where those boundaries fall is the whole trick. We want them at control joints or at natural breaks in the room wherever possible, so there is no visible seam through the middle of an open floor. We also want each section to be a size the crew can take from grind to topcoat in one window, because stopping halfway across an area and resuming the next day is how you get a line you can see forever.

The single most expensive thing that can happen on a commercial job is a member of staff cutting through a cured-but-not-ready area to save thirty seconds.

The noisy hour is the hour to schedule around

Grinding is loud, and with extraction running it is louder. In a workshop nobody cares. In a clinic waiting room, a salon or anywhere with customers trying to hold a conversation, that hour decides when we work at all.

So the grind tends to get moved to the quietest part of the day or out of the day entirely. Nights and weekends are normal for us on commercial work, and that is not a surcharge conversation so much as a sequencing one: a Friday night grind means Saturday is prep and build and Sunday is nothing but cure, which hands you a floor ready for Monday. Dust is contained rather than eliminated, which is why the barrier and the extraction matter more than any promise about cleanliness.

Those two decisions, a barrier you cannot stroll through and a grind booked outside trading hours, are what keep a shop open through the work. The rest of the plan is arithmetic on the cure clock: staff back on it at 12 hours, racking back at 24, anything on wheels at 48.

The cure window is not a negotiation

Everything else on a commercial job can flex. This cannot, and it is the one place we will push back on a schedule rather than agree to something and hope.

Resin cures on a chemical clock, not a convenient one. Foot traffic at 12 hours, heavy items back at 24, vehicles at 48. Humidity moves those numbers around here, which is a reason the window gets longer rather than shorter and a reason we start early in the summer instead of pushing into the afternoon. If somebody walks across a floor before it is ready, you do not get a scuff you can buff out. You get footprints permanently in the finish and a section that has to be ground back and rebuilt, which costs the business far more downtime than waiting would have.

That is why the planning conversation happens up front with whoever actually controls the building. Not the person who booked the job: the person who can say yes to a locked door on Sunday afternoon. We would rather have an awkward discussion about an extra half day than hand over a floor with a shoe print set into it.

What gets decided before the first section

Where things go while we are in a section

Racking, display units, equipment on wheels, anything bolted down. A floor has to be genuinely clear, and the time to work out who moves the heavy items is a week before, not at seven in the morning. Where there is fixed equipment we grind up to it and cut the edge in by hand, which is slower but leaves a clean line rather than a ragged one.

How people and deliveries route around the work

Customers, staff and whoever turns up with a pallet all need a path that does not cross the section. On a shop floor that usually means the front half and the back half swap roles halfway through the job. Deliveries are the ones that get forgotten, so we ask about the delivery days specifically.

What the slab turns out to be hiding

A commercial slab has history. Trenching, patches, old adhesive from whatever flooring was down before, hairline cracks under the racking. A test grind in an inconspicuous corner tells us what the removal involves before a date goes in the diary, so the date we give you is one we can keep. The approach we take on commercial floors around Ellisville starts there every time, and the commercial epoxy page covers how the system gets specified from the traffic rather than from a sheet.

A test grind in an inconspicuous corner tells us what the removal involves before a date goes in the diary.

The seam between sections is a design decision

Where one section meets the next has to be planned, because a resin floor laid in two sittings will always have a line where the wet edge of the first meets the dry edge of the second. On a textured flake build that line disappears into the chip pattern and nobody ever finds it. On a smooth finish it can be visible under certain light forever, which is the main reason we steer large open smooth floors toward being done in one go even if that means a longer closure.

The way around it on a working building is to use what the slab already gives you. Control joints, a threshold, the edge of a doorway, the line where a counter runs: put the break there and the eye reads it as part of the room. That is a conversation worth having at the planning stage rather than discovering afterwards that the seam runs diagonally across the part of the shop everybody stands in.

Who is in the building

There are four of us and no subcontractors. Kevin, Aaron, Kyler and Averie, which on a job that runs through a Saturday night matters more than it does on a garage: the person who agreed the sequence is the person holding the squeegee at two in the morning. Nothing gets relayed through an office and nothing gets quietly reinterpreted by a crew who were not in the original conversation. If you want to see the kind of commercial work this applies to, the finished floors include kitchens and shop spaces.

Scheduling questions we get

Do we have to close while you are here?

Rarely. Most buildings stay open by working in sections with a hard barrier around whatever we are in, and by moving the grinding to nights or weekends. The planning for that happens before the first day rather than during it.

Can you work overnight or on a Sunday?

Yes, and on commercial work it is often the better sequence. A Friday night grind gives us the weekend for the build and the cure, so you walk into a finished floor on Monday instead of losing trading hours midweek.

What happens if somebody walks on it early?

Footprints set into the finish and that section has to be ground back and rebuilt. That is why the barrier is physical and why we will not shorten a cure window to suit a schedule, however much pressure the calendar is under.

Bring us the schedule, not just the square footage

Tell Kevin how the building runs, which hours are quiet and what cannot stop, and we will build the sequence around it before we quote the work. Start with the hours you can give up, because every other decision on the job comes out of that one. We work Ellisville rooms on nights and weekends often enough that it is the normal shape of the week here, not a favor.

601-319-9619

Tell us what the floor is doing now. We will tell you what it takes to fix it.

601-319-9619

icmcoatingmasters@gmail.com
Laurel, MS

Family run since 2021 · Duraflex certified

© 2026 ICM Coating Masters. All rights reserved. About Finishes Gallery Reviews FAQs Sports Courts Offers Refer a Friend Get a Quote Blog Contact